WSDOT to overlay Yelm Ave. E. to Wal-Mart in 2015

Approved by the Yelm City Council Tuesday, October 14:

As the design of the current water main replacement project began, it became apparent that there were additional areas that should be added to the current project.

Area No. 1 is proposed for addition to this contract due to WSDOT grinding and overlaying the full width of Yelm Ave E from the intersection with First St. to the City limits (Wal-Mart area) in the Summer/Fall of 2015. Completing the replacement of this water main on Yelm Ave E from 2nd St SE to 4th St SE [will be] in advance of WSDOT’s project.